Why Is Ofgem Charging Battery Developers to Stay in the Queue?

Ofgem is introducing a new battery storage grid connection fee, charging developers between £3,000 and £25,000 for every megawatt they want to keep in the queue. It is called the Oversubscribed Technologies Commitment Fee, and it exists because the readiness test that fixed the rest of the connections queue cannot fix this one. That problem is volume, not speed.

Rows of containerised battery energy storage units and HV switchgear at a UK grid-connected BESS site, with an engineer in hi-vis inspecting equipment.
TMS GRID | INDUSTRY INSIGHT | NOVEMBER 2026

Why Is Ofgem Charging Battery Developers to Stay in the Queue?

Ofgem is introducing a new battery storage grid connection fee, charging developers between £3,000 and £25,000 for every megawatt they want to keep in the queue. It is called the Oversubscribed Technologies Commitment Fee, and it exists because the readiness test that fixed the rest of the connections queue cannot fix this one. That problem is volume, not speed. Battery projects clear planning faster than almost any other technology, so a disproportionate share of them now hold a protected queue position, around 90GW once operational and Gate 2 capacity are combined, against a 2030 target of just 23 to 27GW. A readiness test cannot shrink a queue built from genuinely real projects. Only a price can.

For most of 2026, the headline story in the UK’s grid connection queue was readiness. NESO’s Gate 2 process asked every developer waiting for a connection to prove their project was real: planning consent, land rights, financing in place, demonstrable progress. It worked. The overall queue fell from more than 700GW to a workable pipeline of around 238GW now being taken forward toward 2035. That success hides two very different problems still sitting inside the same queue, and only one of them is about speed.

The reform still has a speed problem, just not the one battery storage has

NESO asked Ofgem for a second extension to the deadline for issuing the remaining pre-2030 Gate 2 Phase 1 connection offers, pushing it from 30 September to 31 October 2026. Ofgem agreed on 2 October. The extension covers only the roughly 10% of Phase 1 projects still waiting, mostly complex transmission-connected schemes, but it shows the readiness-based reform still has genuine delivery friction to work through: NESO had issued offers to 713 of the 1,223 projects in the 2030 pipeline by that point, about 37GW of the 132GW aligned with Clean Power 2030, with the remainder blocked mainly by late Transmission Owner Construction Offers from National Grid Electricity Transmission rather than by anything the developers themselves had done wrong.

That is a speed problem, and it is the kind a deadline and some pressure from Ofgem can fix. Battery storage has a different problem, and no deadline touches it.

Why did the readiness test let so many batteries through?

Ofgem’s connections methodology protects projects that already hold planning consent, a Capacity Market agreement, or clear near-term delivery, and batteries tend to clear planning faster than almost any other generation technology. That combination let a disproportionate share of battery projects earn a protected Gate 2 position on paper, regardless of whether the UK needs that much battery capacity by the dates in question. A readiness test asks whether a project is real. It was never built to ask whether the country needs a hundred of them.

DESNZ and Ofgem confirmed the scale of the result in a joint open letter: a battery queue of roughly 90GW once operational and Gate 2 capacity are combined, against a Clean Power 2030 target range of 23 to 27GW. That is 14.8GW above the top of the government’s own 2030 range, and 61.7GW above what the system is projected to need by 2035. Every one of those projects can, in the narrow sense Gate 2 tests for, prove it is ready. A readiness test cannot shrink a queue built from genuinely ready projects. Only a price can.

What is the Oversubscribed Technologies Commitment Fee?

The Oversubscribed Technologies Commitment Fee, OTCF for short, is the new battery storage grid connection fee Ofgem is introducing under CMP470, a modification to the Connection and Use of System Code that battery developer Field Energy raised in March 2026. It sets a minimum security and cancellation charge for any technology whose queue capacity runs more than 50% ahead of its own policy target, where that target sits above 5GW. Battery storage is currently the only technology that meets this test, and the fee will charge developers between £3,000 and £25,000 for every megawatt of capacity they want to keep in the queue.

The fee starts at a floor of £3,000 per megawatt. If oversubscription does not fall by at least 25% every six months, the floor climbs in £5,000 steps to a cap of £25,000 per megawatt, then switches off once oversubscription drops below 25%. A 100MW battery project sitting at the top of that scale would need to post a £2.5 million security, returned in full once the project connects, forfeited if it does not.

Ofgem published its minded-to decision on 17 September 2026 and set out its intention to approve the fee. The consultation closed on 1 October, and Ofgem has not yet published a final decision. If the fee is approved as proposed, it enters the Connection and Use of System Code 10 working days after that decision, though it will not start charging anyone straight away.

What happens when the fee actually bites?

The OTCF cannot activate until the reformed queue has settled, specifically after the Gate 2 to Whole Queue transition and the first CMP434 Gated Application Window have both run. On current assumptions, it would first show up in developers’ securities statements in July 2027, with cash payable from October 2027. Inside that window, the fee is designed to force an honest conversation earlier than the market would otherwise have it. A battery project with no secured revenue, no Cap and Floor agreement, no Capacity Market contract, sitting on a Gate 2 position it cannot finance, has every incentive today to keep holding that position, on the chance the economics improve later. A rising per-megawatt security removes that incentive. DESNZ and Ofgem say they expect some merchant-reliant battery projects to exit the queue on their own once the fee comes into view, rather than being pushed out directly.

Not everyone in the industry agrees the mechanism is calibrated correctly. The Electricity Storage Network supports intervening on oversubscription in principle, but it has not backed Ofgem’s original proposal or any of the six alternatives the CUSC workgroup put forward, because its own members cannot agree on the detail. It points out that connection offer costs have in some cases risen sixfold with little explanation from network operators, that Ofgem’s £460 million cost ceiling assumes none of the capacity released by exiting projects gets reused, and that the finance assumptions behind the impact assessment use a rate far below what equity actually costs developers at this stage. Its central request is a joint DESNZ, Ofgem and NESO review of the whole storage policy framework, instead of a fee designed in isolation from the rest of the reform.

The same playbook, twice

Ofgem is reaching for the same tool in another oversubscribed queue. Large data centres face a parallel commitment fee, proposed at between £237,500 and £712,500 per megawatt, aimed at the roughly 73GW of data centre pipeline Ofgem estimates may be speculative. The logic is identical: a readiness test alone cannot tell a project that is genuinely oversubscribing a limited resource apart from one that has simply filled in the right forms. Two fee mechanisms, in two of Britain’s most oversubscribed queues, inside the same year, point to a deliberate pattern rather than a one-off fix. Developers in any technology where protection rules make the readiness bar easy to clear should expect Ofgem to reach for a commitment fee next, not treat the battery storage case as a one-off.

What this means for your project now

For a live battery project holding a Gate 2 position without secured revenue, the question is no longer whether the queue is crowded. It is whether the project can show a financing path that survives a rising per-megawatt security between now and October 2027. Projects with a Cap and Floor agreement or an equivalent revenue contract sit in a materially stronger position than merchant projects relying on wholesale and ancillary service revenue alone, and NESO’s own policy consultation lists restricting future Gate 2 entry to the former as one option under active consideration. Model both ends of the fee range against your project’s capacity and financing timeline now, before the final decision is published. An early, orderly exit from a position that cannot be financed is a better outcome than holding on until the fee forces the decision. And if your project sits in that other 10%, the complex transmission-connected schemes still waiting on a Phase 1 offer, the thing to track now is whether NESO actually met the 31 October date. Neither NESO nor Ofgem has confirmed the outcome publicly yet, and a third extension would say more about the reform’s remaining limits than any fee consultation will.

Where TMS Grid fits

TMS Grid is an Independent Connection Provider delivering high-voltage grid connections, EPC, and Operations and Maintenance across Solar PV, Data Centres, BESS, Wind, EV Charging Infrastructure and Gas Generation in the UK and Ireland. Whether a battery project is holding its Gate 2 position, financing a Cap and Floor agreement, or weighing up an exit, the delivery question is the same: can the connection be built, procured and energised on the timeline the project’s financing depends on. That is the work we do for developers every day.